Issue details
Mainway Project Report
Update on progress from previous report in
March, including proposed purchase of former Skerton High School.
Report requests Cabinet to make considerations around the next
phase of the project.
Decision type: Key
Reason Key: Financial Threshold;
Decision status: Recommendations Approved
Wards affected: Skerton East Ward;
Notice of proposed decision first published: 10/01/2022
Anticipated restriction: Part exempt -
Explanation of anticipated restriction:
Details of the purchase of Skerton School site to be exempt Appendix.
Decision due: 8 February 2022 by Cabinet
Lead member: Cabinet Member with particular responsibility for Finance and Resources
Lead director: Director for Communities and the Environment
Contact: Joanne Wilkinson, Chief Officer - Housing and Property Email: jowilkinson@lancaster.gov.uk.
Consultation process
On-going regular consultation with residents
of Mainway, briefings held with Members and all Councillors
throughout November / December 2022. County Council have been
consulted with regards to the land of the Skerton High
School.
Consultees
Residents, Members, Councillors, County
Council.
Are there any climate change implications?: Expected positive implications as the project continues.
Decisions
- 11/02/2022 - Mainway Project Report
Agenda items
- 08/02/2022 - Cabinet Mainway Project Report 08/02/2022
Documents
- Mainway Project Report