Agenda item

Central Promenade Regeneration Site Marine Road Central Morecambe

Demolition of existing buildings and proposed construction of major mixed leisure development in association with Eden Project (including use classes E, F1 and F2), outdoor arena (including live music performances), public realm, landscaping works, cycle parking, detached shelter and energy pods, and associated infrastructure and engineering operations

Minutes:

A5

21/01113/FUL

Demolition of existing buildings and proposed construction of major mixed leisure development in association with Eden Project (including use classes E, F1 and F2), outdoor arena (including live music performances), public realm, landscaping works, cycle parking, detached shelter and energy pods, and associated infrastructure and engineering operations.

Poulton Ward

A(106 and C)

 

A site visit was held in respect of this application on Monday 24th January 2022 by Councillors Paul Anderton, Victoria Boyd-Power, Dave Brookes, Keith Budden, Roger Cleet, Tim Dant, June Greenwell, Mel Guilding, Cary Matthews, Robert Redfern, Malcolm Thomas and Sandra Thornberry. In attendance were Officers Mark Cassidy, Jennifer Rehman, Lucy Livesey and Eric Marsden.

 

It was proposed by Councillor Robert Redfern and seconded by Councillor Janice Hanson:

 

“That the application be approved subject to the conditions set out in the Committee Report along with the following changes to the conditions:

 

·         Condition 33 removed and hours of deliveries to be captured by condition 27.

·         Condition 17 to include details of play equipment.

·         Additional condition for a scheme for the safe removal and storage of existing public art.”

 

Upon being put to the vote, 11 Councillors voted in favour, with none against and no abstentions, whereupon the Chair declared the proposal to have been carried.

 

Resolved:

 

That the application be approved subject to the conditions set out in the Committee Report along with the following changes to the conditions:

 

·         Condition 33 removed and hours of deliveries to be captured by condition 27.

·         Condition 17 to include details of play equipment.

·         Additional condition for a scheme for the safe removal and storage of existing public art.

 

and subject to the following conditions:

 

1.    Time Limit.

2.    Approved Plans.

3.    Phasing Strategy (construction).

4.    Employment Skills Plan.

5.    Construction Environment Management Plan (CEMP).

6.    Traffic Management Plan (TMP) for construction.

7.    Site Investigation (Remediation Strategy).

8.    Surface Water Drainage Scheme.

9.    Demolition and Construction Phase Surface Water Management Plan.

10.  Foul Drainage Scheme.

11.  Flood Risk Mitigation Scheme.

12.  Geotechnical / structural assessment of the sea wall and details of any retaining structures adjacent to the highway.

13.  Flood Management Plan.

14.  Precise scheme for on-site renewable technology and energy efficient measures.

15.  Details and samples (where relevant) of all external materials, including the construction pattern and cladding of the shell pavilions, window/door details and curtain glazing features and flood gates (pursuant to condition 11).

16.  Details of retaining wall and vegetated embankment with seating to northern façade.

17.  Details and samples precise details of the Energy Pods and Canopy structure, street furniture and boundary features and enclosures.

18.  Lighting scheme.

19.  Security scheme to be agreed with details of CCTV and development to meet Secure by Design standards.

20.  Access and off-site highway scheme to be submitted and agreed including:

               Marine Road Central Improvement Scheme

               Cycle provision improvements connection Marine Road Central to Greenway

               M6 junction calibration

               Shrimp roundabout improvements

               Signage Strategy

21.  Detailed scheme for cycle provision (sheltered and secure).

22.  Landscaping/public realm scheme to be implemented with planting schedule submitted for approval.

23.  Landscape and habitat (BNG) Maintenance and Management Plan.

24.  Collision Monitoring programme (sHRA mitigation).

25.  Additional bat surveys if the existing buildings are not demolished by April 2023 identifying any change and necessary mitigation.

26.  Operation, Maintenance and Verification Report of constructed Sustainable Drainage System.

27.  Delivery, Collections and Service Strategy.

28.  Service access and turning facilities to be provided and retained at all times.

29.  Protocol to define and then restrict size and nature of large scale outdoor events to a maximum of 8 within the summer period only in accordance with the HRA.

30.  Events Management Plan providing require noise assessment and reciprocal noise management practices to mitigate impacts to include flexibility to review for specific events.

31.  Noise Limit for plant to accord with BS4142 Rating Levels.

32.  Construction hours limited to 08:00-18:00 Mon-Fri, 08:00-16:00 on Sat and no working Sundays and bank holidays unless otherwise agreed in writing with the LPA (for exceptional reasons).

33.  BREEAM ‘Excellent’ standard.

34.  Scheme for the safe removal and storage of public art.