Agenda item

Land To The Side Of Willey Lane, Willey Lane, Cockerham

Erection of 17 two storey affordable dwelling houses, associated landscaping and creation of new access for R P Tyson for Construction Ltd

Minutes:

 

A5

13/01018/FUL

Erection of 17 two storey affordable dwelling houses, associated landscaping and creation of new access for R P Tyson Construction Ltd

Ellel Ward

 

A

 

Under the scheme of public participation, Margaret Williams, Philip Irvine, Chris Green and Denis Reilly spoke in objection to the application. Andy Armstrong of Condy & Lofthouse Ltd spoke in support, and Councillor Susie Charles spoke in objection as ward councillor.

 

It was proposed by Councillor Helme and seconded by Councillor Sherlock:

 

“That the application be approved”

 

Upon being put to the vote, 12 members voted in favour of the proposition and 1 against, with 2 abstentions, whereupon the chairman declared the proposition to be carried.

 

Resolved:

 

That planning permission be granted subject to the following conditions, as set out in the case officers report, with the removal of conditions 13 and 14, and variations to conditions 6, 7, 15 and 27:

 

1.

Time Limit – Standard three year consent

2.

Amended plans and documents received – 6th November 2013

3.

Amended documents in relation to tree works received – 13th November 2013

4.

Works must be undertaken in accordance with Arboricultural Impact Assessment dated 6th November 2013

5.

Full Arboricultural Method Statement to be provided

6.

Full details of all hard and soft landscaping to be provided and maintained thereafter

7.

No development to commence until all boundary treatments have been agreed, including secure fencing to the boundary of The Nest, and hedgerow planting to the southern and eastern site boundaries (suitably worded)

8.

No development to commence until details of all external materials have been provided and agreed

9.

Development to be carried out in accordance with the Ecological Survey and mitigation measures proposed

10.

The site internal estate road must be constructed in accordance with LCC Specification for Construction of Estate Roads

11.

Protection of the visibility splays

12.

No development to commence until:

  • The re-alignment of existing kerb lines along the dual carriageway of A588 have been completed
  • Re-location of north bound bus stop to a location on Marsh Lane
  • Scheme for off site highway works including the introduction of TRO on Lancaster Road for the implementation of reducing the speed limits from 40mph to 30mph
  • Once TRO has been successful then creation of variable interactive signs review of public lighting and signage

13.

New vehicular access gates to be set back 2.4m from carriageway

14.

Before vehicular access is used for vehicular purpose the first 2.4m in to site shall be tarmac

15.

Construction management plan including wheel cleaning facilities; dust control; site security; location of site compound, welfare facilities, material storage, contractors parking.

16.

No development to commence until a scheme for construction of a means of access from Lancaster Road has been submitted

17.

No part of the development shall be occupied or opened for trading until conditions 10, 12 and 16 have been constructed and completed

18.

Hours of Construction - 0800-1800 Mon to Fri and 0800-1400 Sat only

19.

Investigation and remediation of contaminated land

20.

Details in relation to the importation of soil, materials & hardcore

21.

Scheme for the prevention of new contamination

22.

Bunding of Tanks containing fuels/solvents

23.

Separate drainage system

24.

Scheme for surface water drainage system

25.

Removal of permitted development rights for Part 1 and Part 2 Schedule 2 of the GPDO.

26.

Removal of permitted development rights for fences and walls

27.

Removal of permitted development rights for outbuildings and for creating areas of hardstanding on front and rear gardens (suitably worded)

28.

The dwellings hereby approved shall be and remain 100% Affordable Housing at all times

29.

Sustainable construction - at least Code level 3

 

 