87 Grand Theatre St Leonards Gate Lancaster Lancashire PDF 362 KB
Relevant Demolition of part of Music Co-op building, single storey toilet block, boundary walls and external stairwells and ramps, and erection of a 2-storey extension to the Grand Theatre, extension of existing car park, construction of a retaining wall, construction of a replacement access ramp and steps, and repair to exposed facades of Music Co-op building.
Minutes:
A6 |
22/00048/FUL |
Relevant Demolition of part of Music Co-op building, single storey toilet block, boundary walls and external stairwells and ramps, and erection of a 2-storey extension to the Grand Theatre, extension of existing car park, construction of a retaining wall, construction of a replacement access ramp and steps, and repair to exposed facades of Music Co-op building. |
Bulk Ward |
A |
It was proposed by Councillor Roger Dennison and seconded by Councillor Robert Redfern:
“That the application be approved subject to the conditions in the Committee Report.”
Upon being put to the vote, 14 Councillors voted in favour of the proposal with none against and no abstentions, whereupon the Chair declared the proposal to have been carried.
Resolved:
That the application be approved subject to the conditions in the Committee Report:
1. Time Limit (3 years).
2. Development to accord with listed plans.
3. Standard contamination condition.
4. Implementation of a programme of archaeological work.
5. Parking and delivery strategy.
6. Surface water drainage details, including percolation tests.
7. Separate foul drainage system.
8. Details of fixtures to the main building (inc. details of connection to exposed window arches).
9. Details and samples of all external materials:
• cladding
• roof materials
• frames
• fin details
• glazing
• external doors
• balustrades and bollards
• surfacing treatments
• external lighting, including any lighting to window arches
• flues and vents
• rainwater goods
• boundary wall
10. Following demolition of extensions and outbuildings, details of stonework repairs to be submitted (including to boundary walls to the south east of the site).
11. Parking and delivery strategy.
12. Construction Management Plan.
13. Cycle storage.
14. Electric Vehicle Charging points.
15. Implementation of parking and turning.