61 Land Off Wyresdale Road Lancaster Lancashire pdf icon PDF 381 KB

Erection of 27 dwellings (C3) with associated access (pursuant to the variation of conditions 2, 5 and 6 on planning permission 18/00472/FUL to amend house types, access, layout, surface water management plans and install a substation).

Minutes:

A8

22/00817/VCN

Erection of 27 dwellings (C3) with associated access (pursuant to the variation of conditions 2, 5 and 6 on planning permission 18/00472/FUL to amend house types, access, layout, surface water management plans and install a substation).

John O’Gaunt Ward

A(106)

 

It was proposed by Councillor Robert Redfern and seconded by Councillor Keith Budden:

 

“That the application be approved subject to the conditions in the Committee Report.”

 

Upon being put to the vote, 14 Councillors voted in favour of the proposal with none against and no abstentions, whereupon the Chair declared the proposal to have been carried.

 

Resolved:

 

That the application for variation of conditions planning permission and a variation to the s106 agreement to reflect this permission in terms of drainage within and beyond the application site be approved subject to the conditions in the Committee Report:

 

1.     Timescale (unchanged).

2.     Approved Plans (varied to submitted plans).

3.     Access construction details (unchanged).

4.     Offsite highway works (unchanged).

5.     Surface water drainage details (unchanged).

6.     Surface water drainage management/maintenance (unchanged).

7.     Finished floor levels (unchanged).

8.     Noise mitigation (unchanged).

9.     External materials (unchanged).

10.  Foul drainage details (unchanged).

11.  Vehicle turning heads (updated to reflect additional information).

12.  Visibility splays (unchanged).

13.  Ecology mitigation (updated to reflect new report).

14.  Arboricultural Impact Assessment (updated to reflect new report).

15.  Arboricultural implications (updated to reflect new report).

16.  Employment skills plan (unchanged).

17.  EV charging (updated to remove cycle storage aspect).

18.  Hard and soft landscaping (unchanged).

19.  Boundary treatments (updated to reflect additional information).

20.  Cycle storage (new condition to reflect additional information).