93 Land North of A683 Bay Gateway, Heaton With Oxcliffe PDF 337 KB
Installation of a 99.9MW battery storage facility with ancillary development including 3m high fencing, battery storage containers, substation, transformers, switchroom, control room, welfare cabin and storage room, construction of internal access points, creation of hardstanding and turning area, erection of gates and 4m high CCTV columns, creation of temporary compound area, raising of land levels and construction of new access onto the A683 Bay Gateway.
Minutes:
A8 |
21/00695/FUL |
Installation of a 99.9MW battery storage facility with ancillary development including 3m high fencing, battery storage containers, substation, transformers, switchroom, control room, welfare cabin and storage room, construction of internal access points, creation of hardstanding and turning area, erection of gates and 4m high CCTV columns, creation of temporary compound area, raising of land levels and construction of new access onto the A683 Bay Gateway. |
Overton Ward |
A(C) |
It was proposed by Councillor Kevin Frea and seconded by Councillor Sandra Thornberry:
“That the application be approved subject to the conditions in the Committee Report.”
Upon being put to the vote, all 13 Councillors voted in favour of the proposal with none against and no abstentions, whereupon the Chair declared the proposal to have been carried.
Resolved:
That the application be approved subject to the conditions in the Committee Report:
1. Timescale.
2. Approved Plans.
3. Highway Works.
4. Tree Protection Plan/AIA.
5. Final Sustainable Drainage Scheme.
6. CEMP.
7. Access Hard Surfacing.
8. Visibility Splays.
9. Colour samples.
10. Landscaping/biodiversity enhancement scheme/management plan.
11. SuDS Operation/Maintenance Plan/Verification Report.
12. Compound removed/land restored.
13. In accordance with CTMP.
14. In accordance with FRA.
15. Nesting Birds.