Issue - meetings

Lune Industrial Estate, New Quay Road, Lancaster

Meeting: 08/11/2021 - Planning Regulatory Committee (Item 38)

38 Lune Industrial Estate, New Quay Road, Lancaster pdf icon PDF 544 KB

Partial demolition and redevelopment of industrial estate including erection of new buildings to create 15 industrial blocks (Use Class B2/B8), erection of amenity block containing nursery, cafe and retail unit (all Use Class E) with associated access, parking and landscaping.

Minutes:

A5

20/01145/FUL

Partial demolition and redevelopment of industrial estate including erection of new buildings to create 15 industrial blocks (Use Class B2/B8), erection of amenity block containing nursery, cafe and retail unit (all Use Class E) with associated access, parking and landscaping.

Marsh Ward

A(106)

 

Under the scheme of public participation, Ward Councillor Mandy Bannon spoke against the application. Jack Appleton (Broadgrove Planning & Development) responded in favour of the application.    

 

COUNCILLOR MANDY BANNON LEFT THE MEETING AT 10:44 A.M.

 

It was proposed by Councillor Robert Redfern and seconded by Councillor Paul Anderton:

 

“That the application be approved subject to the conditions set out in the Committee Report and subject to an S.106 legal agreement to secure financial contributions towards:

 

·       New bus service (£500,000)

·       Travel Plan support (£6,000)

 

and subject to the following revisions to conditions:

 

Conditions 7, 8 and 16:          re-worded to ensure compliance with submitted details

(control conditions).

Conditions 11 and 12:            re-worded to allow demolition to take place before

submission of details.

Condition 14:                          re-worded to require submission pre-occupation.“

 

 

Upon being put to the vote, 9 Councillors voted in favour, 2 against, and none abstained, whereupon the Chair declared the proposal to have been carried.

 

Resolved:

 

That the application be approved subject to an S.106 legal agreement to secure financial contributions towards:

 

·       New bus service (£500,000)

·       Travel Plan support (£6,000)

 

and subject to the conditions set out in the Committee Report:

 

1.     Standard Timescale 3 years.

2.     Approved Plans.

3.     Construction Environment Management Plan.

4.     Protected Species Method Statement (GCN and Bats).

5.     Eradication of Invasive Species.

6.     Employment and Skills Plan.

7.     Contaminated Land.

8.     Asbestos Remediation Plan and Verification Statement.

9.     Sustainable Surface Water Drainage Scheme.

10.  Construction Phase SW Management Plan.

11.  Access, Visibility, Bus Turning and Bus Stop Scheme.

12.  Bus Turning Facility Delivery/Management.

13.  Cycle/footway Scheme.

14.  Travel Plan.

15.  Materials Samples.

16.  Finished Floor levels.

17.  Boundary treatment Details.

18.  Cycle Parking Details.

19.  Landscape Management/Maintenance Plan.

20.  Drainage Management Plan/Verification Report.

21.  Access and off site highway works Provision.

22.  External Lighting and Security Details.

23.  Electric Vehicle Charging Points.

24.  Parking Provision.

25.  Provision of Acoustic Fencing.

26.  Landscaping Implementation.

27.  Nesting Birds.

28.  Development in Accordance with FRA.

29.  Approved Tree Details.

30.  Approved Biodiversity Enhancements.

31.  Separate Foul Drainage System.

32.  No SW Infiltration System.

33.  Plant and Machinery Noise Limit.

34.  Sustainable construction and energy efficiency.

35.  Hours of Operation Restriction (Blocks 13, 14, 15).

36.  Hours of Construction.

37.  Protection of Visibility Splays.

 

and subject to the following revisions to conditions:

 

Conditions 7, 8 and 16:          re-worded to ensure compliance with submitted details

(control conditions).

Conditions 11 and 12:            re-worded to allow demolition to take place before

submission of details.

Condition 14:                           re-worded to require submission pre-occupation.