Land To The Rear Of Pointer Grove And Adjacent To High Road, Halton

Meeting: 27/04/2020 - Planning Regulatory Committee (Item 108)

108 Land To The Rear Of Pointer Grove And Adjacent To High Road, Halton pdf icon PDF 348 KB

Erection of 65 dwellings with associated access, landscaping, open space, drainage, highway and parking arrangements and land re-profiling works

Minutes:

 

Item

Application No

Proposal and Applicant

Ward                                 Decision

 

 

A05

 

18/01422/FUL

 

 

 

Land To The Rear Of Pointer Grove And, Adjacent To High Road, Halton

Erection of 65 dwellings with associated access, landscaping, open space, drainage, highway and parking arrangements and land re-profiling works for Russell Armer Ltd

 

Halton-with-Aughton        A(C)

Ward 

 

 

 

 

 

 

 

 

 

It was proposed by Councillor Robert Redfern and seconded by Councillor Malcolm Thomas:

 

“That, subject to a Section 106 Agreement being entered into to secure the obligations contained in the recommendation of the Committee Report, planning permission be granted, subject to the conditions set out in the Committee Report with an additional condition relating to the hours of construction.”

 

Upon being put to the vote, 8 Councillors voted in favour of the proposition, 1 against and 3 abstained, whereupon the Chair declared the proposal to be carried.

 

Resolved:

 

That, subject to a Section 106 Agreement being entered into to secure the obligations contained in the recommendation of the Committee Report, planning permission be granted, subject to the following conditions:

 

1. Two-year timescale for implementation

2. Development in accordance with approved plans (to be listed)

3. Detailed plans of site access (including internal adoptable standard roads)

4. Offsite highway works

5. Protection of visibility splays

6. Car parking to be provided

7. Electric vehicle charging points

8. Unforeseen land contamination

9. Development in accordance with the submitted Arboricultural Implications Assessment

10. Removal of Permitted Development rights

11. Garage use restriction

12. Provision of landscaping scheme

13. Landscaping management plan

14. Finished floor and site levels

15. Material samples

16. Open Space – provision of 5 pieces of play equipment, maintenance, timetable for   implementation

17. Details of retaining walls and boundary treatments, including finishes.

18. Reasonable avoidance methods for Great Crested Newts and Biodiversity  enhancement (including home owner packs)

19. Development in accordance with the Flood Risk Assessment

20. Development in accordance with the submitted surface water drainage proposals

21. Covered cycle parking and refuse provision

22. Submission of a drainage scheme to account to being phased across the site.

23. Submission of surface water drainage management and maintenance

24. Vegetation removal outside of bird breeding season

25. Arboricultural Method Statement to be submitted

26. Employment and Skill Plan

27. Hours of construction (0800-1800 Mon to Fri and 0800-1400 Sat only)