Meeting: 16/09/2019 - Planning Regulatory Committee (Item 54)

54 St Thomas Centre, Marton Street, Lancaster pdf icon PDF 138 KB

Relevant demolition of existing 2 storey Church Centre building and erection of a replacement 2.5 storey Church Centre building, including covered canopy link to the adjacent Church and alterations to existing carpark, including creation of steps and resurfacing

Minutes:

A9

19/00697/FUL

Relevant demolition of existing 2 storey Church Centre building and erection of a replacement 2.5 storey Church Centre building, including covered canopy link to the adjacent Church and alterations to existing carpark, including creation of steps and resurfacing

Castle Ward

   A(C)

                                                                                        

It was proposed by Councillor Robert Redfern and seconded by Councillor Alan Biddulph:

 

“That Planning Permission be granted, subject to the conditions set out in the Committee Report and an additional condition splitting the materials/details condition into 2 conditions to allow the works to be phased between the new church centre and the existing church building.”

 

Upon being put to the vote, Councillors voted unanimously in favour of the proposition, whereupon the Chair declared the proposal to be carried.

 

Resolved:

 

That Planning Permission be granted, subject to the following conditions:

 

1.         Standard three year timescale.

2.         Approved plans.

3.         Secure contract for construction prior to demolition.

4.         Archaeological watching brief.

5.         Arboricultural Method Statement.

6.         Contaminated land assessment and remediation.

7.         Drainage scheme.

8.         Scheme of highway improvement works: road widening; pedestrian links; road markings; review of street lighting to Peter Street and parking arrangements on Marton Street.

9.         Materials/details for the new church centre - including – stone; render; roofing materials; cladding; eaves verge and ridge details; rooflights; flues and vents; solar panels, boundary treatments, including gates and fencing; surfacing materials; windows and doors including opaque/coloured glazing; window surrounds; heads and cills; barrier to car park; any repairs to the plaque; louvres; details of canopy.

10.       Materials/details for the existing church building - doors.

11.       Landscaping Scheme.

12.       Development in accordance with Arboricultural Implications Assessment.

13.       Surfacing and marking to car park.

14.       Provision of cycle storage.

15.       Inclusion of existing plaque, as shown on the drawings.

16        Hours of construction.