Land Off Imperial Road, Heysham

Meeting: 25/06/2018 - Planning Regulatory Committee (Item 21)

21 Land Off Imperial Road, Heysham pdf icon PDF 376 KB

Erection of an industrial unit (B2) with associated offices (B1), storage and distribution (B8), creation of new access and car parking, provision of surface water attenuation ponds, regrading of land, erection of retaining walls, cycle and smoking shelters and waste compactors

Minutes:

A9

18/00154/FUL

Erection of an industrial unit (B2) with associated offices (B1), storage and distribution (B8), creation of new access and car parking, provision of surface water attenuation ponds, regrading of land, erection of retaining walls, cycle and smoking shelters and waste compactors.

Overton Ward

   A(P)

                                                                                        

It was proposed by Councillor Andrew Kay and seconded by Councillor Colin Hartley:

 

“That the application be approved.”

 

Upon being put to the vote, 12 Members voted in favour of the proposition and 2 against, whereupon the Vice-Chairman declared the proposal to be carried.

 

Resolved:

 

That the application be approved but delegated back to the Planning Manager to resolve the outstanding matters of trees and ecology, and the completion of a legal agreement to secure the shuttle bus service and the off-site highway works and subject to the following conditions:

 

1.

3 year timescale.

2.

Development in accordance with approved plans.

3.

Surface water drainage scheme.

4.

Surface water management scheme.

5.

Foul water drainage scheme.

6.

Contaminated land condition, including the submission of a verification report to demonstrate compliance with the remediation report.

7.

Submission of access details.

8.

Scheme for the provision of off-site highway works.

9.

Transport management plan including:

·         Car parking provision.

·         Management Plan for the car park.

·         Secure and covered cycle parking.

·         Staff Travel Plan.

·         Provision of 9 fast charge electric vehicle charging points.

10.

Submission of finished floor and site levels, including details of retaining structures.

11.

Submission of building materials and lighting details.

12.

Provision of a landscaping scheme and associated management plan.

13.

Ecological mitigation and enhancement.

14.

Environmental Management Plan during the construction period.

15.

Removal of relevant permitted rights.