116 Land Adjacent To Bulk Road, Lancaster
PDF 387 KB
Erection of eight buildings up to eleven
storeys in height to create student accommodation comprising 125
studios (C3), 50 cluster flats (C3/sui generis), 19 shared
townhouses (sui generis), with ancillary communal facilities, study
library (D1), gymnasium (D2), new vehicular and pedestrian
accesses, car parking, servicing bays, public realm and landscaping
for Mr Alex Knapp
Minutes:
|
16/01084/FUL |
Erection of eight buildings up to eleven storeys in height to create student accommodation comprising 125 studios (C3), 50 cluster flats (C3/sui generis), 19 shared townhouses (sui generis), with ancillary communal facilities, study library (D1), gymnasium (D2), new vehicular and pedestrian accesses, car parking, servicing bays, public realm and landscaping for Mr Alex Knapp |
Bulk Ward |
A |
A site visit took place in respect of this item on 7th November 2016 minute 88 (2016/2017) refers.
Under the scheme of public participation, Cheryl Beveridge spoke in objection to the application, the applicant Alex Knapp spoke in support, and Councillor Tim Hamilton-Cox spoke neutrally as Ward Councillor.
It was proposed by Councillor Helen Helme and seconded by Councillor Malcolm Thomas:
“That the application be approved.”
Upon being put to the vote, 13 Members voted in favour of the application, with 2 against, whereupon the Chairman declared the proposal to be carried.
Resolved:
|
That Planning Permission be granted but delegated back to Officers to conclude an issue regarding Television reception, and also subject to the following conditions: |
|
|
|
|
|
1. |
Development to commence within three years. |
|
2 |
List of approved plans. |
|
|
|
|
|
Pre-commencement |
|
|
|
|
3. |
Phasing Plan of the respective blocks. |
|
4. |
Access Details. |
|
5. |
Section 278 highway works. |
|
6. |
Finished Floor Levels. |
|
7. |
Site Investigation. |
|
8. |
Land Contamination Report. |
|
9. |
Construction Management Plan. |
|
10. |
Written scheme of investigation followed by programme of archaeological work. |
|
11. |
Surface Water Drainage Scheme to include maintenance strategy. |
|
12. |
Foul drainage scheme. |
|
|
Above Ground |
|
|
|
|
13. |
Landscaping details. |
|
14. |
Public Realm Surfacing and Landscaping. |
|
15. |
Refuse, provision for drop off and cycle storage (including detail of cycle storage). |
|
16. |
Security Measures (CCTV). |
|
17. |
Glazing Measures. |
|
18. |
Ventilation Measures. |
|
19. |
Building Materials. |
|
|
|
|
|
Pre-occupation conditions |
|
|
|
|
20. |
Travel Plan. |
|
21. |
Servicing and maintenance plan. |
|
22. |
Refuse storage arrangements. |
|
23. |
External lighting. |
|
24. |
Façade cleaning and Maintenance regimes of the elevations. |
|
25. |
Communal Satellite systems. |
|
26. |
Flood evacuation measures. |
|
27. |
Sustainable Energy. |
|
|
|
|
|
Control Conditions
|
|
28. |
Removal of Permitted Development Rights (GPDO 2015 Schedule 2 Part 16 - Communications). |
|
29. |
Student Occupation Only. |
|
30. |
Development in accordance with Flood Risk Assessment. |
|
31. |
Vegetation clearance (only to be undertaken during bird breeding season if ecology walkover undertaken) – the walkover is to include the City Council’s consultee. |
|
32. |
Development in accordance with the AIA. |