83 Sport & Physical Activity Alliance (SPAA) Project Development Updates PDF 62 KB
(Cabinet Member with Special Responsibility Councillor Fletcher)
Report of Corporate Director (Regeneration).
Minutes:
(Cabinet Member with Special Responsibility Councillor Fletcher)
(It was noted that Councillor Bryning had previously declared a personal and prejudicial interest in the following item as a Governor of Morecambe High School. Councillor Bryning left the meeting prior to consideration of this item).
The Corporate Director (Regeneration) submitted a report seeking Cabinet’s approval for two further projects being jointly developed following the adoption of the Sports and Physical Activity Strategy.
The options, options analysis, including risk assessment, were set out in the report as follows:
Options regarding the Cardiac Rehabilitation Project:
Option |
Advantages |
Disadvantages |
Risks |
1, Accept the responsibility to act as accountable body and deliver the Cardiac Phase 4 Project |
Structure and process (externally funded) to deliver this is already in place, no further resources required from the Council. Lead the district in developing new methods and opportunities for increasing participation in sport & physical activity by those most in need
Contribute to the health agenda which could lead to further substantial investment by the PCT
Contribute to LAA targets
|
Additional work for the Active Health Team |
Targets are linked to this funding, possible claw back if targets not met |
2, Not accepting this funding |
No additional targets or responsibility for additional funding
No additional work for the Active Health Team |
Loss of additional funding
Needs of the most in need not met
Possibility that this could lead to loss of further investment from the PCT
Loss of opportunity to contribute to the LAA targets |
Damage to reputation with funders, partners and the community |
Options regarding the Morecambe High School Community Use Agreement:
Option |
Advantages |
Disadvantages |
Risks |
3, Enter into the agreement |
Provides additional opportunities for people to participate in sport and physical activities and improve their health and wellbeing
Address the sport & physical activity needs of children, young people and adults in Lancaster District, specifically the community of Poulton
Funding is in place to deliver this project
Provides training opportunities for young people and adults |
Possible increase in insurance claims
|
Conflicting priorities – Council unable to allocate sufficient resources to support this work, without cutting other service areas. (this would be managed internally by Cultural Services
Unsuccessful implementation – failure to meet objectives
|
4, Not entering into the agreement |
No resources required to oversee the project
No increase in insurance claims |
Lose of some of the (£30,000) Sport England Community Investment Fund allocation and a further substantial amount of match funding (£30,000)
Loss of opportunity to increase participation in sport and physical activity and improve the health and wellbeing of our community
Loss of training opportunities for young people and adults |
Not being able to achieve the targets set out in the agreement with Sports England, leading to possible claw back of funding
Damage to reputation with funders, partners and the community |
Options 1 and 3 is the Officer preferred option.